DMCC Requirements

  • NOC from Developer
  • Fit-out Contractor Appointment Letter from Unit owner or tenant
  • Trade License of Fit-Out Contractor
  • DMCC Trade License/Provisional Approval letter for registration as a DMCC Company
  • DMCC NOC Attn. to EHS for Fit-Out
  • DMCC NOC Attn. to CED for Fit-Out
  • Copy of Sales/Lease Agreement /Tenancy Contract
  • Complete set of Civil, Architecture, and MEP Drawings

Process

  • Contractor/Unit Owner to submit above documents and drawings to Concordia Fit-Out Office
  • Concordia will review documents and drawings ensuring compliance with DMCC requirements
  • Concordia will submit complete set of documents and drawings to DMCC for approval
  • Concordia will collect approved drawings from DMCC and forward to Contractor/Unit Owner

 

Timeline

  • Concordia aim to have approved drawings ready for collection within three working days from the date of receiving complete set of documents and drawings from the fit-out contractor or unit owner

Concordia Fee …….. AED 650