- Contractor to submit complete set of documents and drawings
- Concordia will review documents and drawings and prepare a submittal pack as per CED Standards
- Upon CED notification, Concordia will arrange PRE-NOC Site inspection with CED Inspector
- Concordia will facilitate reply of all queries raised by CED
- Concordia will receive “TRAKHEES-CED APPRAISAL FEE NOTIFICATION†and forward same to Contractor/Unit Owner for their onward settlement
- Concordia will follow up with CED until obtained NOC. After obtaining NOC, Concordia will forward NOC & Approved drawings to Contractor/Unit Owner for their record
TimelineÂ
- Minimum eight working Days from the date of receiving complete set of documents & drawings from Contractor/Unit owner
Concordia Fee ………..AED 1,700 excluding CED FeeÂ