CED Modification NOC

  • Contractor to submit complete set of documents and drawings
  • Concordia will review documents and drawings and prepare a submittal pack as per CED Standards
  • Upon CED notification, Concordia will arrange PRE-NOC Site inspection with CED Inspector
  • Concordia will facilitate reply of all queries raised by CED
  • Concordia will receive “TRAKHEES-CED APPRAISAL FEE NOTIFICATION” and forward same to Contractor/Unit Owner for their onward settlement
  • Concordia will follow up with CED until obtained NOC. After obtaining NOC, Concordia will forward NOC & Approved drawings to Contractor/Unit Owner for their record

Timeline 

  • Minimum eight working Days from the date of receiving complete set of documents & drawings from Contractor/Unit owner

Concordia Fee ………..AED 1,700 excluding CED FeeÂ